Planning Frequency measures the average number of days between two planning cycles impacting order fulfillment

Calculation

Planning Frequency
=
Cycle Duration
2

where

  • Cycle Duration = Days between two planning events (planning cycle in days)

Unit of measure: Days (Calendar days)

Notes

Generally this is a set number of days if planning processes are driven by a planning calendar.

Community Importance Rating:
1.00
(one vote)

Hierarchy

IDNameLevelx
RS1Order Cycle Time1RS1
RS11Planning Frequency2RS11

Process(es)

IDNameLevelx
P1Plan Supply Chain Operations2P1
P101Gather Demand Forecast3P101
P102Validate Demand Forecast3P102
P103Gather Supply (Resources)3P103
P104Balance Supply & Demand3P104
P105Develop Supply Chain Plan3P105
P106Publish Supply Chain Plan3P106
P107Analyze Supply Chain Plan Deviations3P107
P2Plan Source2P2
P201Gather Sourcing Demand3P201
P202Gather Inventory & Schedule3P202
P203Calculate Sourcing Plan3P203
P204Publish Sourcing Plan3P204
P205Analyze Source Plan Deviations3P205
P3Plan Make2P3
P301Gather Demand for Make3P301
P302Gather Inventory & Schedule3P302
P303Calculate Production Plan3P303
P304Publish Production Plan3P304
P305Analyze Make Plan Deviations3P305
P4Plan Deliver2P4
P401Gather Delivery Demand3P401
P402Gather Inventory & Supply3P402
P403Calculate Delivery Plan3P403
P404Publish Distribution Plan3P404
P405Analyze Delivery Plan Deviations3P405
Planning Frequency Order Cycle Time 21100 2 Planning, Frequency, Cycle-time, Responsiveness, Supply Chain The number of days between two planning cycles. For Make-To-Stock supply chains this is the